Roadwork @ Entrance

Repaving of entrance road

Roadwork @ Entrance

Time & Location

Apr 25, 7:00 AM – May 05, 5:00 PM

Porter, 19645 Riverwalk Dr, Porter, TX 77365, USA

About the event

The road improvement project on Riverwalk Dr is expected to begin Tuesday, April 25 and is expected to complete Friday, May 5.  The overlay will take place on the 0.4 mile stretch from FM 1314 to Colorado Dr.  Blading of the road will be the first step which will occur from April 25th to May 1st, then the road will be paved and striped.

The road improvement project on Riverwalk Dr is expected to begin Tuesday, April 25 and is expected to complete Friday, May 5.  The overlay will take place on the 0.4 mile stretch from FM 1314 to Colorado Dr.  Blading of the road will be the first step which will occur from April 25th to May 1st, then the road will be paved and striped.